The activity network below shows the duration of activities A-J and the early and late times at each event.
Find the total float for activities B, D, E, F and J.
For activity B, the late event time at its end node is 9, the early event time at its start node is 0, its duration is 4
Total float of B = 9 - 0 - 4 = 5
Activity D has late event time 12 at its end node, early event time 4 at its start node and duration 3
Total float of D = 12 - 4 - 3 = 5
Similarly for activities E, F and J
Total float of E = 19 - 7 - 7 = 5
Total float of F = 19 - 4 - 6 = 9
Total float of J = 23 - 14 - 4 = 5
The total floats are B:5, D:5, E:5, F:9, J:5